As on 31st March, 2009 (Prov.)
State Owned Shared Projects (RVPN) Central Sector Projects
Others (IPP) Allocation From Unallocated quota
1 STATE OWNED Installed Capacity
(MW)
Raj. Share % Firm capacity
available to Raj. (MW)
             
(a) HYDRO
1 MAHI(2x25+2x45) 140.00   100.00   140.00  
2 ANOOPGARH(3x1.5+3x1.5) 9.00   100.00   9.00  
3 MAHI-RMC(2x0.4+1x0.165) 0.97   100.00   0.97  
4 SURATGARH MH (2x2) 4.00   100.00   4.00  
5 MANGROL MH (3x2) 6.00   100.00   6.00  
6 PUGAL MH (1x1.5+1x0.65) 2.15   100.00   2.15  
7 CHARANWALA (1x1.2) 1.20   100.00   1.20  
8 BIRSALPUR MH (1x0.535) 0.54   100.00   0.54  
             
  SUB-TOTAL (a) 163.85     163.85  
             
(b) THERMAL / GAS
1 KTPS STAGE.I,II,III (2x110+2x210+1x210) 850.00   100.00   850.00  
2 KTPS STAGE.IV (1x195) 195.00   100.00   195.00  
3 RAMGARH GAS (1x3) 3.00   100.00   3.00  
4 RAMGARH GAS (1x35.5) 35.50   100.00   35.50  
5 RAMGARH GAS EXTN. (2x37.5) 75.00   100.00   75.00  
6 SURATGARH STAGE - I (2x250) 500.00   100.00   500.00  
7 SURATGARH STAGE - II (2x250) 500.00   100.00   500.00  
8 SURATGARH STAGE -III (1x250) 250.00   100.00   250.00  
9 GIRAL STAGE-I UNIT-1&2(2x125) 250.00   100.00   250.00  
10 DHOLPUR GTPP UNIT-1(1x110) 110.00   100.00   110.00  
11 DHOLPUR GTPP UNIT-1I(1x110) 110.00   100.00   110.00  
12 DHOLPUR GTPP UNIT-1II(1x110) 110.00   100   110.00  
13 SURATGARH STAGE -IV Unit-I(1x250) 250.00   100.00   250.00  
  SUB-TOTAL (b) 3238.50     3238.50  
  SUB-TOTAL A(a+b) 3402.35     3402.35  
(B) Non-Conventional (Wind,Biomass)            
1 WIND POWER ,RREC 41.550   100.00   41.550  
2 WIND POWER,RSMML 37.300   100.00   37.300  
3 WIND POWER,(Investors of Suzlon Energy Limited) 340.450   100.00   340.450  
4 WIND POWER,(Investors of Enercon India Limited) 270.370   100.00   270.370  
5 WIND POWER (NEPC) 0.675   100.00   0.675  
6 M/S KALPATARU POWER LTD.(BIOMASS) 15.800   100.00   15.800  
7 M/S CHAMBAL POWER LTD. (BIOMASS) 7.500   100.00   7.500  
8 M/S AMRIT ENVIROMENTAL POWER LTD. (BIOMASS) 8.000   100.00   8.000  
9 Wind Power 43.150   100.00   43.150  
10 WIND POWER (VESTAS) 1.200   100.00   1.200  
  SUB-TOTAL (B) 765.995     765.995  
  TOTAL-1 (A+B) 4168.345     4168.345  
2 SHARED PROJECTS (RVPN)        
(a) HYDRO        
  1 - B.B.M.B. COMPLEX        
(a) Bhakra Left Bank(5x108) 540.00   15.22   82.18  
(b) Bhakra Right Bank (5x157) 785.00   15.22   119.48  
(c) Kotla (1x29.25+1x24.2+1x24.2) 77.65   15.22   11.82  
(d) Ganguwal (1x29.25+1x24.2+1x24.2) 77.65   15.22   11.82  
(e) Dehar (6x165) 990.00   20.00   198.00  
(f) Pong (6x66) 396.00   58.50   231.66  
  2 - CHAMBAL COMPLEX        
(a) Gandhi Sagar (5x23) 115.00   50.00   57.50  
(b) Rana Pratap Sagar (4x43) 172.00   50.00   86.00  
(c) Jawahar Sagar (3x33) 99.00   50.00   49.50  
  SUB-TOTAL (a) 3252.30     847.95  
           
(b) THERMAL        
  SATPURA (5x62.5) 312.50   40.00   125.00  
           
  SUB-TOTAL (b) 312.50     125.00  
           
  TOTAL-2 (a+b) 3564.80     972.95  
         
3 CENTRAL SECTOR PROJECTS Installed Capacity
(MW)
Raj. Share % Available capacity to Raj. (MW)  
  ALLOCATION
           
(a) HYDRO (NHPC/JVNL/THDC)        
1 TANAKPUR(3x31.4) 94.20   11.53   10.861  
2 SALAL STAGE -I & II (690) 690.00   2.95   20.355  
3 CHAMERA -I (3x180) 540.00   19.60   105.840  
4 URI (4x120) 480.00   8.96   43.008  
5 CHAMERA -II (3x100) 300.00   9.67   29.010  
6 NJPS (6x250) (SJVNL) 1500.00   7.47   112.000  
7 DHAULI GANGA (4x70) 280.00   9.64   27.000  
8 TEHRI STAGE-I(UNIT-I TO IV)(4X250) (THDC) 1000.00   7.50   75.000  
9 DULHASTI HEP(UNIT-I TO III)(3X130) 390.00   10.88   42.420  
           
  SUB-TOTAL (a) 5274.20     465.49  
           
(b) THERMAL / GAS (NTPC)        
1 SINGRAULI (5x200+2x500) 2000.00   15.00   300.00  
2 RIHAND TPS STAGE-I (2x500) 1000.00   9.50   95.00  
3 RIHAND TPS STAGE-II (2x500) 1000.00   10.00   100.00  
4 ANTA GAS (3x88.71+1x153.2) 419.33   19.81   83.07  
5 AURIYA GAS (4x111.19+2x109.3) 663.36   9.20   61.03  
6 DADRI GAS (4x130.19+2x154.5) 829.76   9.28   77.00  
7 UNCHAHAR TPS STAGE - I(2x210) 420.00   4.76   20.00  
8 UNCHAHAR TPS STAGE - II(2x210) 420.00   9.05   38.00  
9 UNCHAHAR TPS STAGE - III(1x210) 210.00   10.95   23.00  
10 KAHAI GAON STAGE-II(3x500),UNIT-I & 2(2x500) 1000.00   4.86   48.60  
11 E.R. (IN LIEW OF TALA-6X170=1020MW)            
  (i) Farakka(0.38%+2.09%) 1600   2.47   39.52  
  (ii)Kahalgaon(0.38%+6.14%) 840   6.52   54.77  
  (iii)Talchar(0.38%) 1000   0.38   3.80  
  SUB-TOTAL (b) 11402.45     943.79  
           
(c) NUCLEAR (NPC)        
1 RAPP(1x100+1x200) 300.00   100.00   300.00  
2 NAPS (2x220) 440.00   10.00   44.00  
3 RAPP EXTN. (1x220) Unit-3 220.00   28.41   62.50  
4 RAPP EXTN. (1x220) Unit-4 220.00   28.41   62.50  
           
  SUB-TOTAL (c) 1180.00     469.00  
           
  TOTAL- 3 (a+b+c) 17856.65     1878.29  
INSTALLED CAPACITY EXCLUDING NES PROJECTS:
  GRAND TOTAL (1+2+3) 25589.80     7019.59  
         
4 Allocation From Unallocated quota varies from time to time as per orders issued by NREB      
       
           
  Capacity added during April 2008 to 31st March 2009 Increase in Installed Capacity (MW) / Comm. Date Raj. Share % Available capacity to Raj. (MW)  
1 WIND POWER,(Investors of Enercon Energy Limited) 16.00/April-08   100   16.00  
2 WIND POWER,(Investors of Enercon Energy Limited) 4.00/May-08   100   4.00  
3 WIND POWER,(Investors of Enercon Energy Limited) 3.75/May-08   100   3.75  
4 WIND POWER,(Investors of Enercon Energy Limited) 13.60/Sept-08   100   13.60  
5 WIND POWER,(Investors of Suzlon India Limited) 8.4/Aug-08   100.00   8.40  
6 WIND POWER,(Investors of Suzlon India Limited) 73.85/Sept-08   100.00   73.85  
7 WIND POWER,(Investors of Suzlon India Limited) 7.5/Dec-08   100.00   7.50  
8 WIND POWER,(Investors of Suzlon India Limited) 29.35/Jan-09   100.00   29.35  
9 WIND POWER,(Investors of Enercon Energy Limited) 1.5/Mar-08   100.00   1.5  
10 Giral Stage-IUnit-2(1x125) 125/26-12-08   100.00   125.00s  
11 Kahalgaon Stage-II(3x500), Unit-2(1x500) 30-12-08   4.86   24.30  
12 Wind Power March-09   100   43.15  
13 STPS Stage-IV U-1(1x250) 250/31-3-09   100.00   250.00  
  TOTAL INCREASE     598.90  